Cost of project and means of finance, with projected P&L, cash flow and DSCR
A single format from the The Detailed Project Report pack. Layout for the financial section of a DPR; Rs lakh unless stated.
- 5 pages
- 371
- Word and PDF
- 16 September 2026
What it covers
- 1Cost of project and means of finance, with projected P&L, cash flow and DSCRLayout for the financial section of a DPR; Rs lakh unless stated
Read the opening
The first part of the format, as it downloads. Blanks are highlighted.
Statement 1 — Cost of project
# | Particulars | Amount | Basis and annexure |
|---|---|---|---|
1 | Land and site development | [ ] | Allotment letter / deed — Ann. N |
2 | Buildings and civil works | [ ] | Chartered engineer's estimate — Ann. K |
3 | Plant and machinery — indigenous | [ ] | Quotations — Ann. J |
4 | Plant and machinery — imported (CIF [ ] + duty [ ] + freight and clearing [ ]) | [ ] | Quotations; duty computation — Ann. J |
5 | Electrical installation, DG set and utilities | [ ] | Quotations |
6 | Effluent treatment and pollution control equipment | [ ] | Quotations; consent conditions |
7 | Miscellaneous fixed assets (handling, furniture, IT, vehicles [if eligible]) | [ ] | Quotations |
8 | Technical know-how, licence fee and intellectual property | [ ] | Agreement — Ann. L |
9 | Preliminary and pre-operative expenses | [ ] | Estimate with break-up |
10 | Contingency at [ ]% on items 2 to 7 | [ ] | Computation |
11 | Interest during construction | [ ] | Drawdown schedule at [ ]% for [ ] months |
12 | Margin money for working capital | [ ] | Working capital assessment — Statement 5 |
Total cost of project | [ ] | ||
Of which eligible for [scheme] as defined in [clause ___ of the guidelines]: Rs [ ] lakh (items [ ]; items [ ] are excluded by that clause) | |||
Statement 2 — Means of finance